You are the designer. FIREAXIS is the tool installers, electricians, architects and design offices use to lay out their fire detection, have the coverage checked, and produce a calculation note that points to the applicable clauses — based on the Belgian standards NBN S 21-100-1:2025 and NBN S 21-112-3:2025.

NBN S 21-100-1 — automatic detection NBN S 21-112-3 — audible alarm Addressable systems only Drawings DXF · DWG · IFC · PDF Calculation note per room, with clause references 2025 editions, in force since 17 July 2025
The problem

A detection layout is three problems in one.

Placing detectors is not a matter of symbols: it is a coverage calculation under normative constraints. In practice you do it by hand, under deadline pressure. That is exactly what the platform takes over — without ever deciding for you.

Time

Time you cannot invoice

Going through every room — height, ceiling type, occupancy, ventilation and obstructions — to derive coverage area and spacing: hours of spreadsheet work for a single floor.

Coverage

Blind spots you cannot see

A detector too close to a wall, a beam crossing the ceiling, a narrow room, a sloped ceiling: in each case the real coverage is smaller than the drawing suggests.

Proof

Compliance you have to prove

At commissioning, every choice has to be explainable. Without a calculation note tied to the drawing, the conversation with the inspection body turns into rework on site.

What the platform does

You place. It calculates, checks and documents.

From concept design to commissioning, on new buildings and existing installations alike. The file stays yours : the platform signs nothing, it makes every choice verifiable.

Lay out on your drawing

You import the drawing, outline the rooms, and place detectors, manual call points and sounders. The platform keeps up : zone division, detection type allowed per room, coverage area and spacing recalculated at every move.

You get : the laid-out drawing + the take-off

Document every position

Every position is tied to the clause that governs it : monitored area, critical distance, height, slope, sound levels used. That is what you defend at commissioning — and it is generated instead of written.

You get : the calculation note, room by room

Check an existing layout

Already have a layout ? Transfer it and run the check : rooms wrongly exempted, zones outside the allowed limits, insufficient coverage, oversized equipment. Every deviation is named and shown at the exact place it occurs.

You get : the list of deviations, clickable on the drawing

Bring an existing system up to standard

Survey the installed system, test it against the standard in force, and extract what is missing : what to move, to add, to remove. Prioritised, and ready to price.

You get : the gap against the standard + the remedial take-off

Onboarding and support

The one place where Fire Axis steps in alongside the tool : getting started with the platform, method for finding your way through the standard, classic pitfalls, design trade-offs. On your real projects, with your drawings. No normative document is handed out or projected : everyone works from their own copy of the standards they apply.

Format : working session
FIREAXIS platform — early access

A calculation engine, not a symbol library.

You import the drawing. You describe the rooms. You place the devices where the site allows — and the engine measures what each one really covers, then hands you back the drawing and its calculation note.

  • Coverage demonstrated — maximum area and critical distance applied room by room, according to ceiling height, use and slope.
  • The hard cases included — clearance to walls, ceiling beams and obstructions, narrow rooms, sloped ceilings, suspended ceilings and raised floors.
  • Volume, not just plan — shafts, ducts and roof voids are read in three dimensions, where a top view says nothing any more.
  • You stay in control — every position stays movable, and the check recalculates immediately.
FIREAXIS — study in progress
OPEN-PLAN OFFICE · 323 m² CIRCULATION · 244 m² WORKSHOP · 526 m² NOT COVERED D max 7,0 m L3L2 L1GF SHAFT — VOLUME VIEW sampling column aspirator, outside the duct D max 7,0 m measured in volume APEX ROOF — VOLUME VIEW ridge 3 devices aligned on the ridge · 32° pitch 94 dB(A) 82 dB(A) 76 dB(A) 68 dB(A) at the bedhead 7 short 78 dB(A) at the bedhead SOUND FIELD — CALCULATED LEVEL HALL · threshold 65 dB(A) BEDROOM · threshold 75 dB(A) the threshold follows the use : warn at 65 dB(A), wake at 75 OBSCURED column VIDEO DETECTION — WHAT IT SEES a camera does not cover, it LOOKS : whatever comes between takes the rest away and it sees nothing in the dark — 15 lux minimum in the image

You place, the engine measures. A badly placed device leaves a gap : its radius turns red, and goes back to green as soon as it covers.

A shaft is judged in three dimensions. The sampling column runs down on the aspirator side, and the aspirator stays outside the duct — where it can be reached.

Ceiling shape changes the rule. Under an apex roof the row follows the ridge ; on a single pitch or a sawtooth roof, it sits differently.

The threshold is not the same everywhere. 65 dB(A) in a hall, 75 dB(A) at a bedhead : 68 dB(A) passes in one and fails in the other.

Video detection does not cover an area : it sees. Its range is a line of sight, and every obstruction takes away what it hides — lighting then becomes a detection requirement.

How you work

Four steps, one complete file

ÉTAPE 01

Your drawing, your scale

You import the drawing (DXF or PDF) and calibrate it against a printed dimension. It is the one step everything else depends on : a wrong scale makes every area wrong.

STEP 02

Your normative decisions

Level of surveillance, exempted rooms, occupancy and height of each room, detection type suited to the risk. You decide ; the platform derives the applicable limits, Table by Table.

STEP 03

Your layout, checked

You place the devices where the site allows. The coverage radius colours live — green, amber, red — and one button tests the whole floor against the standard, clause by clause.

STEP 04

Your file, documented

Laid-out drawing, take-off, loop routing and calculation note : exportable as PNG, PDF and DXF. It is your file and your signature — every figure carries the reference of the clause behind it.

Who it is for

Technical counterparts, one shared language

Architects

See early what detection imposes on ceilings, suspended ceilings and builder's openings — before the services package discovers them.

Design offices

A reproducible, traceable coverage calculation that you run yourself and can put in front of the inspection body.

Electricians & installers

A reliable take-off to price accurately, a loop route that saves cable, and positions that do not force rework on site.

Building managers

A clear picture of what is installed and a route to compliance you can budget for.

Frequently asked questions

What we are asked most often

Which standards does the platform rely on ?

On the 2025 editions, in force since 17 July 2025. They separated what used to be combined : the NBN S 21-100 series now covers only automatic detection — zones, detector types, coverage areas and spacings, manual call points — while the NBN S 21-112 series governs the alarm, including NBN S 21-112-3 for sounders and the levels to be reached. The platform implements NBN S 21-100-1:2025 and NBN S 21-112-3:2025, and the edition used is printed on every document it produces : a calculation run on an outdated version is worthless, and that must be visible. Every verdict cites the clause it rests on : you can check it, and challenge it. Requirements specific to your project — regional regulations, fire service instructions, insurer's requirements — remain your judgement : the platform does not know them.

Is the platform suitable for a conventional installation ?

No. FIREAXIS handles addressable systems only, and it is better to know that before creating an account than after. This is not an arbitrary limit : everything the platform does rests on a device being IDENTIFIABLE one by one — the loop and its isolators, the number of components per circuit, the schedule that goes out for quotation, the check that names the room at fault. On a conventional system the unit is no longer the device but the wired zone ; the rules for wiring, zoning and verification are not the same, and applying them to a conventional drawing would produce a wrong file with the appearance of a correct one.

Which drawing formats does the platform accept ?

DXF preferably : the geometry is already structured there. A PDF or an image works just as well, provided the scale is calibrated against a printed dimension — and that is the step not to rush : a title block stating the wrong scale is the most common defect, and it makes every area wrong, and therefore the whole detector count.

Does the platform replace the designer, or the inspection body ?

Neither, and that is deliberate. You are the designer : the platform places nothing on your behalf, it reads what you have placed and tests it against the standard. The file carries your signature, not ours. And regulatory validation remains the responsibility of the approved body that commissions the installation : the tool prepares commissioning by making every choice verifiable, it does not pronounce it.

Do my drawings and projects leave my hands ?

Your projects live in your own space, separate from every other user's. Nobody else reaches them — not even a peer working on the same building, for the same client. One single exception, tightly bounded : to troubleshoot for you, Fire Axis can open your file for two hours at most. That access is recorded in your account — date and reason — and a banner shows it for as long as it lasts. A project becomes visible to someone only if you invite them, and you withdraw that whenever you want.

Everything exports at any time : the file as PDF, the project as a single file you take with you. And if you stop your subscription, your earlier projects remain viewable and exportable : they are yours, you made them.

Who can read my projects ?

You, and the people you invite onto a specific project — for that project only. The guest creates their own account ; they inherit none of your other files. On the handover date you set, guest access expires on its own.

Fire Axis resells nothing, cross-references nothing and exploits none of your drawings. The only data that leaves the platform is what you export yourself.

Do you need to be a standards specialist to use it ?

No : that is precisely the point. Every tool explains what it does, every non-compliance is written in plain language before being tied to its clause, and one click shows it at the exact place on the drawing. You do, however, need to know your building — the heights, the uses, the doors, the beams : no drawing states those, and the platform asks you for them.

Is the FIREAXIS platform available ?

It is in early access. It is opening gradually to installers, electricians, design offices and architects who use it on their real projects and steer its development — their feedback decides what gets built next. Write to us to be in the next wave.

Contact

Take control of your detection layouts.

Every account is opened by hand : you tell us who you are, we open it. Reply within two working days.

Tell us about a project

A design question, a rule, a deadline. Reply within two working days.

Your details are used solely to handle your request. They are neither resold nor used for any other purpose.

What you should know

The platform helps you design and check. It does not certify.

No approval, no certification. FIREAXIS is neither an inspection body nor a certification body. It issues no certificate of conformity. Regulatory validation remains the responsibility of the approved body that commissions the installation, and responsibility for the design remains with the designer who signs the file.

It does not replace the standard. The documents produced refer to the applicable clauses ; they reproduce neither the text, nor the tables, nor the figures — these are protected by NBN's copyright. Users are expected to hold their own copy of the standards they apply.

Editions implemented : NBN S 21-100-1:2025 and NBN S 21-112-3:2025, in force since 17 July 2025. Any change to the texts is carried through and dated ; the edition used appears on every export.

What the calculation is. A design estimate, run on the data you enter — scale, heights, uses, partitions, equipment. It is worth what that data is worth. Sound levels in particular remain an estimate : the proof is still on-site measurement.